Current issues · Chapter 37

Hot topics

What assessors expect you to know now, and why it matters to your projects. Updated between editions.Last updated 16 November 2026.

Updated 16 November 2026

Building Safety Act: gateways and timescales

Hard-stop gateways for higher-risk buildings remain a critical-path risk. Know the statutory periods and what actually happens.

  • Higher-risk building: at least 18 m or 7 storeys, with at least two residential units.
  • Gateway 2 (before work starts): statutory period 12 weeks for a new HRB, 8 weeks for work to an existing HRB. Decisions have often taken far longer; allow a realistic programme margin.
  • Major changes during construction need BSR approval (6 weeks); notifiable changes must be notified before the work is done.
  • Gateway 3 (before occupation): statutory period 8 weeks. Occupying before the completion certificate and registration is a criminal offence.

Why it matters to a PM: design maturity before Gateway 2, change control after approval, and Gateway 3 in the handover programme.

Practise:Programming and planningLegal/regulatory complianceManaging projectsHealth and safety

Updated 16 November 2026

The Building Safety Regulator becomes a standalone body

The BSR left the HSE on 27 January 2026, a first step towards a single construction regulator.

  • The BSR is the building control authority for all higher-risk building work in England and regulates the building control profession.
  • It became a standalone body, sponsored by MHCLG, on 27 January 2026.
  • The government consulted on a single construction regulator in December 2025.

Practise:Legal/regulatory complianceHealth and safety

Updated 16 November 2026

The Building Safety Levy

A charge on most new residential development in England for building control applications from 1 October 2026.

  • Payable by the developer, calculated on floor area at rates set for each local authority.
  • 50% discount for previously developed land; exemptions include affordable and social housing and developments of fewer than 10 dwellings.
  • The completion certificate is not issued until the levy is paid.

Why it matters: appraisals, budgets and the timing of building control applications.

Practise:Project financeLegal/regulatory complianceDevelopment/project briefs

Updated 16 November 2026

RICS standard on responsible use of AI

Mandatory for RICS members and regulated firms from 9 March 2026 wherever AI materially affects a surveying service.

  • Record whether AI use is material, and why.
  • Firms keep a register of AI systems and an AI risk register, reviewed at least quarterly.
  • Apply professional judgement to outputs: AI does not transfer responsibility.
  • Tell clients in writing, in advance, when and how AI will be used.
  • APC candidates must not use generative AI to produce their submission.

Practise:Ethics, Rules of Conduct and professionalismData managementClient care

Updated 16 November 2026

New RICS CPD rules

From 1 January 2026: 20 hours a year, with three mandatory topics every three years.

  • 20 hours a year, of which 10 structured.
  • Mandatory topics every three years: ethics; AI, data and technology; sustainability.
  • Record CPD by 31 January following each CPD year and sign the annual declaration.

Practise:Ethics, Rules of Conduct and professionalism

Updated 16 November 2026

Payment reform and the proposed retentions ban

The Commercial Payments Bill would ban cash retentions in construction contracts two years after it comes into force.

  • Government response to the late payment consultation (24 March 2026): ban on cash retentions, 60-day maximum payment terms for large businesses paying SMEs, mandatory statutory interest.
  • The Bill was introduced in the House of Lords on 19 May 2026 and moved to the Commons in October 2026.

Why it matters: contract drafting, security for defects (bonds, insurance) and cash flow forecasts.

Practise:Contract practiceCommercial managementProject finance

Updated 16 November 2026

Failure to prevent fraud

A corporate offence for large organisations from 1 September 2025, under the Economic Crime and Corporate Transparency Act 2023.

  • Applies to large organisations meeting two of: more than 250 employees, more than £36 million turnover, more than £18 million total assets.
  • Defence: reasonable fraud prevention procedures.

Why it matters: procurement integrity, valuations and claims, and supply chain due diligence.

Practise:Ethics, Rules of Conduct and professionalismProcurement and tendering

Updated 16 November 2026

Future Homes Standard

Applies to most new homes from 24 March 2027: low-carbon heating, solar PV and better fabric.

  • Published 24 March 2026. Transitional relief where the building control application is made before 24 March 2027 and work starts before 24 March 2028; higher-risk buildings follow from 24 September 2027.
  • The notional dwelling assumes an air source heat pump and rooftop solar PV, so a home with a gas boiler will not pass.
  • Compliance is checked at design and at completion, with photographic evidence of build quality.

Why it matters to a PM: bring in the energy assessor early, fix the heating and PV strategy before planning, and control substitutions.

Practise:SustainabilityConstruction technology and environmental servicesDevelopment/project briefs